B & S Contracts & Design Ltd v Victor Green Publications Ltd [1984] ICR 419
Contract – Exceptions clause – Strike – Threats – Payment under threat
Facts
The plaintiffs were contracted to erect stands at Olympia for an exhibition. The contract specified that the Plaintiffs would make every effort to complete the works, but it was subject to a force majeure clause. The Plaintiffs brought over workers from a company of theirs that had become insolvent and was making the workers redundant. When the workers arrived, they stopped work, demanding a lump sum severance payment to which they were not entitled. The demand was eventually reduced to £9,000. The Plaintiffs were prepared to contribute £4,500 but refused the defendants’ offer to advance the remaining £4,500 against the contract price. They indicated that the work would not continue unless the defendants paid that sum in addition to the agreed price. The Defendants paid it and on the completion of the works, they deducted the funds from the Plaintiffs’ invoice. The Plaintiffs brought an action. The defendants claimed duress.
Law Teacher writing support
Writing a law essay?
We choose a writer who is an expert in your area of law and qualified to at least the academic level you select. Most of our writers hold a master’s degree or PhD, have teaching experience, or both.
Send us your question and, if you wish, any marking criteria. We’ll write an essay to your instructions.
Issues
Whether the Plaintiffs could rely on the force majeure clause to justify non-performance, and whether the additional payment was recoverable because it had been made under economic duress.
Decision / Outcome
The appeal by the Plaintiffs was dismissed. The additional payment had been made under economic duress. There was a veiled threat not to perform the contract unless the defendants paid the extra £4,500. The defendants could not obtain another workforce in time, and failure to erect the stands threatened grave damage to their reputation and potentially heavy claims from exhibitors. As such, in the circumstances they had no practical alternative but to pay it.
The Plaintiffs were unable to rely on the force majeure clause because they had not made the reasonable efforts required to avoid the effect of the strike. In these particular circumstances, the defendants’ proposed advance would have enabled them to pay the workforce, but they unreasonably insisted on an additional payment instead. The court did not hold that a contractor must always yield to a strike demand. Nor does every threatened breach of contract or unwillingly accepted variation amount to duress.
The defendants acted promptly by deducting the £4,500 from the invoice rather than affirming the additional payment once the pressure had ended. They were entitled to recover it in that way, so the Plaintiffs’ claim failed.
Judgment transcript. Report: [1984] ICR 419. Parallel references: [1984] 1 WLUK 1197; (1984) 81 LSG 893; (1984) 128 SJ 279.