BLACK FRIDAY
20%OFFSITEWIDE

Any product. As many orders as you like.

USE CODEBLACKFRIDAY2026
Order now

Ends 28 November · 23:59 UK time

Cannot be used with another coupon.

Disclaimer: This work was produced by one of our expert legal writers, as a learning aid to help law students with their studies.

Any opinions, findings, conclusions, or recommendations expressed in this material are those of the authors and do not reflect the views of LawTeacher.net. Any information contained in this case summary does not constitute legal advice and should be treated as educational content only.

DSND Subsea Ltd v Petroleum Geo Services ASA [2000] EWHC 185 (TCC)

936 words (4 pages) Case Summary

07 Mar 2018 Case Summary Reference this LawTeacher

Jurisdiction / Tag(s): Contract law UK Law

DSND Subsea Ltd v Petroleum Geo Services ASA [2000] EWHC 185 (TCC); [2000] BLR 530

Technology and Construction Court, 28 July 2000. Economic duress, misrepresentation and contractual termination.

Dyson J rejected PGS’s attempt to avoid a contract variation for economic duress or misrepresentation. He also held that its subsequent termination notice was invalid. The case distinguishes illegitimate pressure from commercial bargaining and shows why termination must comply with the particular contractual procedure invoked.

The contract and dispute

DSND contracted with PGS Offshore Technology AS to perform subsea work at the Banff oilfield. Although Petroleum Geo Services ASA appears first in the case title, the contracting party was PGS Offshore Technology AS, referred to as PGS in the judgment.

Law Teacher writing support

Writing a law essay?

We choose a writer who is an expert in your area of law and qualified to at least the academic level you select. Most of our writers hold a master’s degree or PhD, have teaching experience, or both.

Send us your question and, if you wish, any marking criteria. We’ll write an essay to your instructions.

The work included installing flexible risers connecting the seabed to a floating production vessel. The parties changed their installation plans, leaving payment and insurance issues to be resolved. On 25 September 1998 they signed a memorandum of understanding (MOU) revising payment arrangements, the work schedule and protection against risks associated with the riser interface equipment. An October memorandum of agreement (MOA) provided for another vessel, Rockwater’s Semi 2, to assist.

PGS later alleged that the September agreement resulted from a misrepresentation about DSND’s vessel, the Fennica, and economic duress. On 19 November it purported to terminate the contract for failing to provide a suitable diving support vessel from 10 November. Dyson J determined preliminary issues at trial.

Why the misrepresentation claim failed

PGS relied on a statement that the Fennica could operate in a significant wave height of three metres. Dyson J found that DSND’s representative had expressed an expectation, based on experience rather than calculations, and had qualified it by reference to buoyancy sections and crew safety and comfort. PGS’s technically qualified representatives would have understood that further work was required before a reliable conclusion could be reached.

The statement was therefore not an actionable representation in the circumstances. The judge also found that PGS had not relied on it when entering the MOU. By then, PGS knew that substantial parts of the operation required conditions of no more than two metres. The September negotiations principally concerned payment and insurance. The later communications relied on did not establish the alleged repeated representation.

PGS also failed to establish that the vessel lacked the relevant capability. Alternatively, even if an inducing misrepresentation had been proved, rescission would have been barred. PGS had affirmed and relied on the MOU after learning of the alleged problem, while DSND incurred substantial obligations to Rockwater. These were distinct reasons for rejecting PGS’s case.

Economic duress and commercial pressure

Dyson J identified three requirements for actionable duress: pressure producing compulsion or a lack of practical choice; illegitimacy of that pressure; and a significant causal connection between the pressure and entering the agreement.

Relevant factors included an actual or threatened breach of contract, good or bad faith, realistic alternatives, protest and subsequent affirmation. The existence of commercial pressure did not by itself establish duress.

DSND had suspended assembly of the riser interface units while seeking adequate insurance or indemnity protection. Its concern was genuine and reasonable. The equipment was untried, and a failure during installation could have serious consequences. Dyson J said that, even if the suspension amounted to a breach, it did not constitute illegitimate pressure in these circumstances.

That did not establish a general right to suspend work. The contract contained no suspension provision. Nor did the judge accept that DSND had refused to resume work until PGS met its payment demands. The negotiations involved concessions on both sides and were ordinary commercial bargaining.

The judge was also unpersuaded that PGS lacked a realistic alternative. It had access to legal advice and contractual termination options. Its principal negotiator had not explored alternative vessels, and there was no contemporaneous written protest supporting the alleged duress.

Alternatively, PGS had affirmed the MOU after any pressure had ceased. It continued to insist on compliance with that agreement and eventually relied on an alleged breach of it to terminate. The court would therefore have refused to set it aside even if duress had initially been established. The dependent challenges to the October agreement consequently did not arise.

Why the termination was invalid

The termination notice relied specifically on the absence of a suitable diving support vessel from 10 November. The court found no relevant breach. The agreed schedule had contractual effect, but its dates were indicative, and diving work was to follow completion of riser installation. That installation was not completed until about 20 November.

DSND had also taken reasonable steps to obtain a vessel. The market was tight, the programme uncertain, and booking an expensive vessel far in advance on standby would not have served PGS’s interests. The Semi 2 was suitable for diving work and had already performed some of it.

There was a separate obstacle to termination under article 16.1: PGS had to identify the situation and give DSND a reasonable opportunity to remedy it, with a warning of termination. Even assuming a relevant breach, that opportunity had not been given. The court treated this as an alternative ground, rather than a finding that DSND had breached the contract.

PGS could not recast its notice as termination without cause under article 16.3. The two routes carried fundamentally different financial consequences, and PGS had elected to use article 16.1.

Outcome

The challenges based on misrepresentation and economic duress failed, and the termination notice was invalid. As PGS conceded would follow from invalidity, its notice repudiated the contract. DSND was entitled to accept that repudiation and had done so. The judgment resolved preliminary issues rather than awarding a quantified sum of damages.

Source: Full judgment (BAILII).

LawTeacher

LawTeacher

LawTeacher.net is the UK’s leading provider of academic legal support, offering both writing services and an extensive collection of law study resources for students in the UK and overseas.

Founded in 2003 by Grey’s Inn graduate Barclay Littlewood, the Company was built on a commitment to excellence, with unique guarantees and a high standard of service from day one.

The team includes over 500 UK legally qualified writing experts, with many practising solicitors and barristers, and several former lecturers.

Areas of Legal Expertise

Contract Law Criminal Law Constitutional and Administrative Law EU Law Tort Law Property Law Equity and Trusts Jurisprudence Company Law Commercial Law Family Law Human Rights Law Employment Law Evidence Public International Law Legal Research and Methods Dispute Resolution Business Law and Practice Civil Litigation Criminal Litigation Professional Conduct Taxation Wills and Administration of Estates Solicitors’ Accounts

Cite This Work

To export a reference to this article please select a referencing stye below:

Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.

Related Services

View all

Related Content

Jurisdictions / Tags

Content relating to: “Contract law”

Related Articles

Prices from

£ 99

Estimated costs for: Undergraduate 2:2 • 1000 words • 7 day delivery

Place an order

Delivered on-time or your money back

Give yourself the academic edge today

Each order includes

  • On-time delivery or your money back
  • A fully qualified writer in your subject
  • In-depth proofreading by our Quality Control Team
  • 100% confidentiality, the work is never re-sold or published
  • Standard 7-day amendment period
  • A paper written to the standard ordered
  • A detailed plagiarism report
  • A comprehensive quality report