Disclaimer: This work was produced by one of our expert legal writers, as a learning aid to help law students with their studies.

Any opinions, findings, conclusions, or recommendations expressed in this material are those of the authors and do not reflect the views of LawTeacher.net. Any information contained in this case summary does not constitute legal advice and should be treated as educational content only.

SABIC UK Petrochemicals Ltd v Punj Lloyd Ltd [2013] EWHC 2916 (TCC)

818 words (4 pages) Case Summary

07 Mar 2018 Case Summary Reference this LawTeacher

Jurisdiction / Tag(s): Contract law UK Law

SABIC UK Petrochemicals Ltd v Punj Lloyd Ltd [2013] EWHC 2916 (TCC)

High Court, Technology and Construction Court; Stuart-Smith J; 10 October 2013.

The court upheld SABIC’s contractual termination of a construction contract for failure to proceed with due diligence and deterioration in the contractor’s financial position. However, the contractor’s conduct did not amount to repudiatory breach. The distinction mattered: a right to terminate under an express clause did not depend on establishing a common-law right to terminate.

Facts

In 2006, SABIC engaged Simon Carves Ltd (SCL) to design and construct a low-density polyethylene plant at Wilton for £135 million. SCL was a subsidiary of Punj Lloyd Ltd, which provided a parent company guarantee in June 2008 and was the defendant to SABIC’s claim. SCL subsequently entered administration in 2011.

Law Teacher writing support

Writing a law essay?

We choose a writer who is an expert in your area of law and qualified to at least the academic level you select. Most of our writers hold a master’s degree or PhD, have teaching experience, or both.

Send us your question and, if you wish, any marking criteria. We’ll write an essay to your instructions.

After delays and disputes, the parties made a further settlement agreement in July 2008. This increased the contract price, provided for substantial advance payments and incorporated a completion plan. The critical date for introducing ethylene into the plant for commissioning was fixed at 5 December 2008.

Progress continued to fall behind. SABIC gave a written warning on 3 October 2008 and terminated on 3 November. It then arranged completion of the project, using the principal subcontractors. The litigation concerned the validity and financial consequences of that termination, including money received under a performance bond and advance payment guarantee.

The contractual obligations

SCL had to carry out and complete the works with due diligence. A separate obligation required it to achieve the agreed ethylene-in date. The contract permitted termination where, despite a written warning, SCL failed to proceed with due diligence. It also permitted termination if deterioration in SCL’s financial position jeopardised its ability adequately to perform.

SABIC argued that diligence had to be assessed against the contractual objectives. SCL and Punj Lloyd argued that the court also had to recognise what completion date was realistically achievable and that diligence did not require the impossible or necessarily require acceleration.

What due diligence required

Stuart-Smith J distinguished an obligation to achieve a result from an obligation to work diligently towards it. Missing the contractual date would breach the former, but would not necessarily establish a breach of the latter. Delay could provide evidence of deficient performance; it was not automatically conclusive.

Diligence required work to be pursued industriously, efficiently and expeditiously, judged against the contract’s objectives rather than a standard reduced to match this contractor’s difficulties. Depending on the circumstances and the contractual terms, it could require acceleration.

Nor did an apparently unattainable deadline remove the obligation. If the agreed result could no longer be achieved, diligence remained directed towards the nearest possible approximation to proper performance, including minimising continuing delay. The judge also recognised the express qualification for SABIC’s own contractual failures where those failures affected SCL’s ability to perform.

Why termination was valid

The findings went beyond the bare fact of delay. They included inadequate resources, poor planning and management, failures to procure and manage necessary subcontractor services, and an inadequate response to continuing slippage. Those failures justified the October warning and persisted during the period before termination.

The warning sufficiently identified the breach. The contractual provision did not require SABIC to prescribe a detailed remedial programme. Although the warning specified seven days, a month in fact elapsed before termination, giving SCL adequate time to demonstrate that it was addressing the problems.

The financial ground also succeeded. The question was whether deterioration created a substantial jeopardy to performance, rather than a minor or fanciful risk. Financial constraints had affected resourcing and the response to delay. Support from the parent company did not establish that SCL had the resources needed to perform this particular contract.

Nevertheless, the judge rejected repudiatory breach. SCL’s failures were serious, but it still intended to complete the works. On the facts, its conduct came close to, but did not cross, the threshold for repudiation. SABIC therefore succeeded on its express contractual termination rights.

The financial result

The court found a balance of £11,797,514 due to SABIC, with statutory interest to be considered separately. The counterclaim seeking repayment of the bond and guarantee proceeds failed. SABIC’s lost-revenue claims were excluded by the contractual provision covering loss of production or profit.

The 20% aggregate liability cap did not automatically limit the entire termination account. The judge distinguished liabilities for breaches of obligation from the contractual accounting exercise on termination. He also held, as an alternative conclusion, that if the cap applied to that account, the bond proceeds would be credited before applying it.

Significance of the decision

The case shows why progress, diligence and termination must be analysed separately. Failure to meet a deadline does not itself prove a lack of diligence, while persistent failures in resources and management can justify termination under the wording of an express clause. Equally, valid contractual termination does not necessarily establish repudiatory breach: the two questions require their own analysis.

Read the judgment on BAILII.

LawTeacher

LawTeacher

LawTeacher.net is the UK’s leading provider of academic legal support, offering both writing services and an extensive collection of law study resources for students in the UK and overseas.

Founded in 2003 by Grey’s Inn graduate Barclay Littlewood, the Company was built on a commitment to excellence, with unique guarantees and a high standard of service from day one.

The team includes over 500 UK legally qualified writing experts, with many practising solicitors and barristers, and several former lecturers.

Areas of Legal Expertise

Contract Law Criminal Law Constitutional and Administrative Law EU Law Tort Law Property Law Equity and Trusts Jurisprudence Company Law Commercial Law Family Law Human Rights Law Employment Law Evidence Public International Law Legal Research and Methods Dispute Resolution Business Law and Practice Civil Litigation Criminal Litigation Professional Conduct Taxation Wills and Administration of Estates Solicitors’ Accounts

Cite This Work

To export a reference to this article please select a referencing stye below:

Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.

Related Services

View all

Related Content

Jurisdictions / Tags

Content relating to: “Contract law”

Related Articles

Prices from

£ 99

Estimated costs for: Undergraduate 2:2 • 1000 words • 7 day delivery

Place an order

Delivered on-time or your money back

Give yourself the academic edge today

Each order includes

  • On-time delivery or your money back
  • A fully qualified writer in your subject
  • In-depth proofreading by our Quality Control Team
  • 100% confidentiality, the work is never re-sold or published
  • Standard 7-day amendment period
  • A paper written to the standard ordered
  • A detailed plagiarism report
  • A comprehensive quality report