Legal Case Summary
Hoenig v Isaacs [1952] 2 All ER 176
The performance of a contract and the right to terminate for repudiatory breach.
Facts
A contract was concluded for the redecoration of a one-room flat for the lump sum of £750. Upon completion, there remained an outstanding of balance of £350 for the contractor’s work and labour. There were certain defects in the bookcase and wardrobe, the cost of repair of which was £55. The employer refused payment of the outstanding balance, claiming a repudiatory breach of the contract due to a failure to perform the contract.
Issues
The question arose as to whether the entire performance of the contract was a condition precedent to payment.
Decision / Outcome
As a matter of law, the Court held that whether the entire performance of a contract is a condition precedent to payment depends on the construction of the specific contract. In the case of a contract for work and labour for a lump sum payable upon completion, the Court held that a contractual promise to complete the work is an innominate term of the contract and not a condition precedent to payment. In such contracts, an employer cannot deprive the contractor of any payment for completed work due to the presence of some defects. Only breaches that ‘go to the root of the contract’ entitles the employer to repudiate liability and refuse payment. On the facts, the work under the contract had been completed and the defects did not go to the root of the contract. As the employer is taking the benefit of the completed work under the contract, the entire performance of the works is not construed as importing a condition precedent to the stipulated payment, but solely as an innominate term giving rise to damages for defects. Thus, the employer was bound to pay the contract price, yet entitled to deductions for the defects.
Updated 19 March 2026
This case summary remains legally accurate. Hoenig v Isaacs [1952] 2 All ER 176 continues to be good law and is regularly cited in English contract law as a leading authority on the doctrine of substantial performance and the distinction between entire and severable contracts. The principles described — that whether entire performance is a condition precedent to payment depends on construction of the contract, and that only breaches going to the root of the contract entitle an employer to withhold all payment — remain well established and have been applied and affirmed in subsequent case law, including Bolton v Mahadeva [1972] 1 WLR 1009, which is frequently read alongside this case as a contrasting authority. There have been no statutory or judicial developments that materially alter the position as described. Readers should note, however, that the article’s characterisation of the contractual promise to complete as an “innominate term” reflects one way of framing the analysis, and some academic commentary approaches the substantial performance doctrine slightly differently; but this does not undermine the core legal propositions stated. The summary is suitable for study purposes.