Disclaimer: This work was produced by one of our expert legal writers, as a learning aid to help law students with their studies.

Any opinions, findings, conclusions, or recommendations expressed in this material are those of the authors and do not reflect the views of LawTeacher.net. Any information contained in this case summary does not constitute legal advice and should be treated as educational content only.

RTI Ltd v MUR Shipping BV [2024] UKSC 18

1,456 words (6 pages) Case Summary

21 Mar 2026 Case Summary Reference this LawTeacher

Jurisdiction / Tag(s): Contract law UK Law

MUR Shipping invoked a force majeure clause when US sanctions impeded contractual payment in US dollars. RTI offered to pay in euros instead. The Supreme Court held that reasonable endeavours in force majeure clauses do not require the affected party to accept non-contractual performance, absent clear wording.

Background

MUR Shipping BV (shipowner) and RTI Ltd (charterer) entered into a contract of affreightment on 9 June 2016 for the carriage of bauxite from Guinea to Ukraine. Freight payments were to be made in US dollars. On 6 April 2018, the US Office of Foreign Assets Control (OFAC) imposed sanctions on RTI’s parent company, United Company Rusal plc. Although RTI itself was not directly listed, as a majority-owned subsidiary it was subject to the same restrictions. The sanctions did not prohibit US dollar payments under the contract. It was common ground that timely payment was highly unlikely because a US intermediary bank would initially stop the transfer pending investigation.

Law Teacher writing support

Writing a law essay?

We choose a writer who is an expert in your area of law and qualified to at least the academic level you select. Most of our writers hold a master’s degree or PhD, have teaching experience, or both.

Send us your question and, if you wish, any marking criteria. We’ll write an essay to your instructions.

On 10 April 2018, MUR served a force majeure notice under clause 36 of the contract, asserting that the sanctions prevented contractual payment in US dollars. RTI rejected the notice and offered to pay in euros instead, undertaking to bear any additional costs or exchange rate losses suffered by MUR in converting euros to US dollars. MUR refused, insisting on its contractual right to payment in US dollars, and suspended performance by refusing to nominate vessels. RTI commenced arbitration claiming damages for the cost of chartering replacement vessels during the period of suspension. On 25 April 2018, after the US authorities extended permission to maintain or wind down affected contracts, MUR resumed nominating vessels and accepted euro payments.

The Issue

The central issue was whether the exercise of reasonable endeavours under a force majeure clause may require the party affected to accept an offer of non-contractual performance from the other contracting party in order to overcome the effects of the force majeure event or state of affairs. Clause 36.3(d) of the contract provided that a force majeure event must be one that “cannot be overcome by reasonable endeavors from the Party affected.”

The Decisions Below

The arbitrators held that the force majeure event could have been overcome by MUR accepting RTI’s offer to pay in euros, and that MUR had therefore breached the contract. On appeal, Jacobs J reversed that decision, holding that reasonable endeavours did not extend to accepting non-contractual performance. The Court of Appeal majority (Males and Newey LJJ) restored the arbitrators’ award, holding that the force majeure state of affairs was “overcome” if its adverse consequences were completely avoided by the offered alternative. Arnold LJ dissented, agreeing with Jacobs J that clear wording was required before a party could be required to accept non-contractual performance.

The Court’s Reasoning

General Principle, Not Narrow Interpretation

The Supreme Court rejected the Court of Appeal majority’s approach that the issue was merely one of interpretation of the particular word “overcome” in clause 36.3(d). Lords Hamblen and Burrows held that the reasonable endeavours proviso is a very common feature of force majeure clauses, whether express or implied, and that the issue raised was one of general application requiring resolution as a matter of principle:

We are therefore not dealing with an unusual feature, but rather a very common feature, of a force majeure clause.

The Object of Reasonable Endeavours Provisos

The Court held that the underlying rationale of reasonable endeavours provisos is one of causation. A party is excused from performance only where the failure to perform is caused by the force majeure event. If the affected party can reasonably prevent the failure, the cause is the party’s own inadequate response rather than the event itself. Critically, however, this causal inquiry must be assessed by reference to the parameters of the contract:

The relevant question is whether reasonable endeavours could have secured the continuation or resumption of contractual performance. It is reasonable steps towards that end with which the reasonable endeavours proviso is concerned. It is not concerned with the steps that could or should have been taken to secure some different, non-contractual, performance. The object of the reasonable endeavours proviso is to maintain contractual performance, not to substitute a different performance.

Applying this to the facts, the Court held that the impediment to contractual performance — banking delay for US dollar payments — remained in place and was not “overcome” by offering non-contractual performance in euros:

Put another way, it would be absurd to say that MUR caused the non-performance of the contract by failing to accept an offer of non-contractual performance.

Freedom of Contract

The Court emphasised the fundamental principle of freedom of contract, including the freedom not to accept non-contractual performance:

The principle of freedom of contract includes freedom not to contract; and freedom not to contract includes freedom not to accept the offer of a non-contractual performance of the contract.

Clear Words Required to Forego Valuable Contractual Rights

MUR had an undoubted contractual right to insist on payment in US dollars. The Court held that a party should not be required to forego a valuable contractual right unless the contract makes clear that was the parties’ intention:

In our judgment, clear words would be necessary for MUR to be required to forego that valuable right, including making clear the circumstances in which that would be so required. Neither of these matters are addressed by clause 36.3(d).

Certainty in Commercial Contracts

The Court identified substantial practical problems with RTI’s proposed test, which would require inquiries into whether acceptance of non-contractual performance would involve “no detriment” and would “achieve the same result” as contractual performance. The Court held that these inquiries gave rise to considerable legal and factual uncertainty, including questions about what constitutes detriment, when it is to be assessed, and how to identify and match the “purpose” underlying contractual obligations. The Court observed:

It is not unmeritorious or unjust to insist on contractual performance, all the more so if being precluded from doing so would introduce uncertainty contrary to the expectations of reasonable business people.

The Authorities

The Court found strong implicit support in Bulman & Dickson v Fenwick & Co [1894] 1 QB 179 and Reardon Smith Line Ltd v Ministry of Agriculture, Fisheries and Food [1963] AC 691 (the Vancouver Strikes case). In Bulman, charterers were entitled to insist on their contractual right to have cargo unloaded at a strike-bound berth even though it would have been reasonable to divert to an unaffected berth. As Pollock B stated in that case:

It is not a question between the plaintiffs and defendants as to what is reasonable or unreasonable, it is a question of contract between the parties.

In the Vancouver Strikes case, the House of Lords held that charterers were not required to exercise options to load alternative cargo even though that was the only way to avoid delay. The Court found the present case was even stronger because MUR had no option at all to accept euros — there was no contractual alternative.

The authorities relied upon by RTI were found to provide weak or no support. B & S Contracts and Design Ltd v Victor Green Publications Ltd [1984] ICR 419 was distinguished because the offer in that case was merely early contractual performance, not non-contractual performance. Payzu Ltd v Saunders [1919] 2 KB 581 concerned mitigation of loss after breach, which is a fundamentally different question from whether a breach has occurred. The Suez frustration cases were held to be inapplicable because frustration operates differently from force majeure clauses, and in The Eugenia the alternative route was in fact contractual performance.

Practical Significance

This decision establishes as a matter of general principle that, absent clear express wording, a reasonable endeavours proviso in a force majeure clause does not require the affected party to accept an offer of non-contractual performance from the other contracting party, regardless of whether such acceptance would cause the affected party no detriment. The decision prioritises certainty and predictability in commercial contracts over a broad evaluative test of reasonableness. It confirms that the focus of reasonable endeavours is on achieving contractual performance as defined by the terms of the contract. Parties wishing to extend reasonable endeavours obligations to encompass acceptance of non-contractual performance must do so by clear express provision. The decision is of wide significance for the interpretation of force majeure clauses in English commercial law, particularly in international trade contracts.

Verdict: The Supreme Court unanimously allowed MUR Shipping BV’s appeal, holding that MUR was entitled to rely on the force majeure clause and was not required to accept RTI’s offer of non-contractual performance (payment in euros instead of US dollars). The decision of the majority of the Court of Appeal was reversed.

Reported citations: [2024] 1 Lloyd’s Rep 621, [2024] 2 WLR 1350, [2024] 4 All ER 623, [2024] Bus LR 1492, [2025] AC 675

Source: RTI Ltd v MUR Shipping BV [2024] UKSC 18

LawTeacher

LawTeacher

LawTeacher.net is the UK’s leading provider of academic legal support, offering both writing services and an extensive collection of law study resources for students in the UK and overseas.

Founded in 2003 by Grey’s Inn graduate Barclay Littlewood, the Company was built on a commitment to excellence, with unique guarantees and a high standard of service from day one.

The team includes over 500 UK legally qualified writing experts, with many practising solicitors and barristers, and several former lecturers.

Areas of Legal Expertise

Contract Law Criminal Law Constitutional and Administrative Law EU Law Tort Law Property Law Equity and Trusts Jurisprudence Company Law Commercial Law Family Law Human Rights Law Employment Law Evidence Public International Law Legal Research and Methods Dispute Resolution Business Law and Practice Civil Litigation Criminal Litigation Professional Conduct Taxation Wills and Administration of Estates Solicitors’ Accounts

Cite This Work

To export a reference to this article please select a referencing stye below:

Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.

Related Services

View all

Related Content

Jurisdictions / Tags

Content relating to: “Contract law”

Related Articles

Prices from

£ 99

Estimated costs for: Undergraduate 2:2 • 1000 words • 7 day delivery

Place an order

Delivered on-time or your money back

Give yourself the academic edge today

Each order includes

  • On-time delivery or your money back
  • A fully qualified writer in your subject
  • In-depth proofreading by our Quality Control Team
  • 100% confidentiality, the work is never re-sold or published
  • Standard 7-day amendment period
  • A paper written to the standard ordered
  • A detailed plagiarism report
  • A comprehensive quality report