Aberdeen City and Shire Strategic Development Planning Authority v Elsick Development Company Limited [2017] UKSC 66

1,081 words (5 pages) Case Summary

03 Nov 2026 Case Summary Reference this LawTeacher

The UK Supreme Court held that a Scottish planning authority could not lawfully require developers, through supplementary guidance and planning obligations, to pay into a pooled transport fund where a development’s connection with some of the works was only trivial. Such a payment did not restrict or regulate the development of the payer’s land, as section 75 of the Town and Country Planning (Scotland) Act 1997 requires, and it could not be treated as relevant to the grant of planning permission. The Court dismissed the authority’s appeal, so the quashing of the guidance stands.

The proposed fund

The Aberdeen City and Shire Strategic Development Planning Authority anticipated substantial development and major extra transport investment to deal with its combined effects. A cumulative transport appraisal put that additional cost at £86.6 million, above public schemes already committed. The authority proposed a Strategic Transport Fund. Statutory supplementary guidance, forming part of the development plan, would require developers in strategic growth areas to pay fixed sums into a pool. For housing, the sums ran from £1,350 for a one-bedroom unit to £3,148 for a unit of five bedrooms or more. The money would be spent only on listed interventions.

Law Teacher writing support

Writing a law essay?

We choose a writer who is an expert in your area of law and qualified to at least the academic level you select. Most of our writers hold a master’s degree or PhD, have teaching experience, or both.

Send us your question and, if you wish, any marking criteria. We’ll write an essay to your instructions.

Elsick Development Company Limited proposed about 4,000 houses and other facilities near Stonehaven. It objected that the expected contribution was out of all proportion to the demands its development would make, and contrary to Circular 3/2012. That Circular advised authorities to seek planning obligations only where stated tests were met, including that an obligation fairly and reasonably related in scale and kind to the development and related to it directly or through cumulative impact. Elsick nevertheless entered a section 75 obligation with Aberdeenshire Council, agreeing to contribute if the guidance was valid. Outline permission was granted.

A reporter had warned that the relationship between contributing developments and the infrastructure was not sufficiently clear and direct. The plan was amended to say that contributions would support only related projects necessary to make the developments acceptable. The authority adopted the guidance after adding, at the Scottish Ministers’ request, a statement that planning obligations would follow the Circular.

The scale of the connection

The guidance treated the fund as addressing cumulative impacts at identified hotspots, while each developer still had to mitigate impacts specific to its own development. It said a developer could assess and mitigate cumulative impact outside the fund. Lord Hodge rejected the argument that this made payment voluntary. The guidance said the alternative would require a much more comprehensive assessment and would definitely be more time-consuming and almost certainly more expensive, if achievable at all. Unless the developer could do that work and persuade the authority that it was robust, the scheme envisaged that permission would be refused.

The traffic evidence showed why pooling mattered here. The Elsick development would generate much of the traffic on one proposed link. On several other routes its contribution was negligible. Yet its payment could be spent on the whole list. The Supreme Court accepted the Inner House’s finding that some connections were absent or trivial.

The Court of Session

The Inner House quashed the guidance. It distinguished sharing the cost of infrastructure that several developments together made necessary from requiring them to fund a list of projects irrespective of whether their development contributed to the need.

The limits on planning obligations

Lord Hodge, with whom Lord Neuberger, Lady Hale, Lord Mance and Lord Reed agreed, treated the lawfulness of the required obligation as the central issue. A planning condition must be imposed for a planning purpose, must fairly and reasonably relate to the permitted development, and must not be unreasonable in the Wednesbury sense. A planning obligation is not confined to what could be imposed as a condition. Under section 75, a person may agree, or undertake unilaterally, to restrict or regulate the development or use of land, including by paying money. Beyond those words, the power must be used for a planning purpose and must not be Wednesbury unreasonable.

A payment obligation under section 75 must restrict or regulate the use or development of the burdened land. Several developers can share the cost of infrastructure where each contributes to the cumulative need. Making the start of construction conditional on paying for an unrelated improvement cannot supply the missing link. Otherwise an authority could extract benefits unrelated to the planning merits of the site.

Whether an obligation is relevant to the grant of permission is a separate question. Section 37(2) requires regard to the development plan so far as material to the application and to other material considerations. In Tesco Stores Ltd v Secretary of State for the Environment, the House of Lords held that an offered obligation is material only if its connection with the development is more than trivial. An unconnected offer is an attempt to buy permission. A development-plan policy cannot make an irrelevant obligation relevant. The Circular is national guidance and must be considered, but departing from it after considering it is a matter of planning judgement, not in itself an error of law.

Why this scheme was unlawful

The scheme was not unlawful merely because it departed from the Circular. It was unlawful for two reasons. First, fixed pooled contributions would be spent on infrastructure with which a development had no more than a trivial connection. The payment was therefore not imposed for a purpose relating to the development and use of the burdened site. In Elsick’s case there was a further defect: the obligation did not itself postpone development until payment. The council resolved to grant permission but to issue it only once the obligation had been entered. The obligation neither restricted nor regulated the development and was outside section 75.

Secondly, a trivial connection meant that the obligation could not be a material consideration. The authority could not require a developer to enter an irrelevant obligation as a precondition of permission. The statement that obligations would follow the Circular was inconsistent with the scheme and provided no safeguard. Lord Hodge accepted that the fund had practical advantages and noted that England and Wales had legislated for a community infrastructure levy, but held that the 1997 Act does not authorise this scheme. A local development land levy would require legislation.

Verdict: The Court unanimously dismissed the authority’s appeal. The order quashing the guidance stood. Section 75 permitted contributions for infrastructure connected to the developments that created the need, but did not authorise this transport fund.

Source: Aberdeen City and Shire Strategic Development Planning Authority v Elsick Development Company Limited [2017] UKSC 66

LawTeacher

LawTeacher

LawTeacher.net is the UK’s leading provider of academic legal support, offering both writing services and an extensive collection of law study resources for students in the UK and overseas.

Founded in 2003 by Grey’s Inn graduate Barclay Littlewood, the Company was built on a commitment to excellence, with unique guarantees and a high standard of service from day one.

The team includes over 500 UK legally qualified writing experts, with many practising solicitors and barristers, and several former lecturers.

Areas of Legal Expertise

Contract Law Criminal Law Constitutional and Administrative Law EU Law Tort Law Property Law Equity and Trusts Jurisprudence Company Law Commercial Law Family Law Human Rights Law Employment Law Evidence Public International Law Legal Research and Methods Dispute Resolution Business Law and Practice Civil Litigation Criminal Litigation Professional Conduct Taxation Wills and Administration of Estates Solicitors’ Accounts

Cite This Work

To export a reference to this article please select a referencing stye below:

Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.
Reference Copied to Clipboard.

Related Services

View all
Prices from

£ 99

Estimated costs for: Undergraduate 2:2 • 1000 words • 7 day delivery

Place an order

Delivered on-time or your money back

Give yourself the academic edge today

Each order includes

  • On-time delivery or your money back
  • A fully qualified writer in your subject
  • In-depth proofreading by our Quality Control Team
  • 100% confidentiality, the work is never re-sold or published
  • Standard 7-day amendment period
  • A paper written to the standard ordered
  • A detailed plagiarism report
  • A comprehensive quality report